
<center><span class="news-text_italic-underline">Judgment Date: 1 August 2025</span></center>
The parties’ contract contained an LCIA arbitration clause providing that an appeal on a question of law could be filed in the 30 days after “the decision is rendered”. The clause also purported to allow appeals on fact and excluded the right to bring applications under sections 67 and 68 of the <span class="news-text_italic-underline">Arbitration Act 1996</span> (“<span class="news-text_medium">AA 1996</span>”).
An LCIA tribunal rendered its award and the LCIA delivered it to the parties at a later date. The claimant filed a section 69 application within 30 days of delivery but outside of the 30 days from the date of the award. The Commercial Court rejected the application as out of time and the claimant sought permission to appeal to the Court of Appeal.
The Court of Appeal dismissed the application, holding that the contractual thirty-day period ran from the date of the award, not its delivery. Males LJ, giving the leading judgment, emphasised:
The Court also held that the parties’ waiver of rights excluded the ability to seek an extension of time under section 79(1) AA 1996. Even if such an application were possible, Bryan J had been correct in the Commercial Court to state he would not have granted relief and under section 79(6) because there was no jurisdiction to appeal that refusal without permission from the lower court.
The decision confirms that where parties agree a contractual timeline for appeals, the period will run from the date the award is made unless the contract expressly provides otherwise. It also illustrates the limits on party autonomy under the AA 1996, with attempts to exclude mandatory rights of challenge or to allow appeals on fact being ineffective. Parties must therefore take care to calculate deadlines for challenges from the award date rather than from notification, to avoid applications being struck out as out of time.